Set in Stone Phase 3 Begins

With funding now assured via generous grants from the Massachusetts Historic Commission (MHC) and the Robinson-Broadhurst Foundation, UUCW has officially launched Phase 3 of our masonry repairs. Phase 3 focuses on repairs to the leaky “valley” between the bell tower and main roof.
On July 13 we welcomed a site visit from Paul Holtz, our assigned Project Manager from MHC, and Douglas Manley, Principal Architect of the Spencer Preservation Group. Both gentlemen will work closely with us throughout Phase 3. Paul will monitor our progress and make sure we adhere to the State’s grant requirements and to our Preservation Restriction that is permanently in place for our building. Doug will produce the construction plans and documents against which contractors will bid, and will oversee execution against those plans. Jill Sackett will serve as the Project Coordinator for UUCW.
Our meeting began in the back of the church sanctuary, underneath the ceiling area that is damaged by water seeping in from the valley.


In the picture below, Jill, Doug and Paul study the valley area and discuss the general scope of Phase 3. The visit included a trip up the dusty ladders to the interior top of the tower…not for the faint of heart.

We expect to have construction documents ready for bid by the end of August.